- Home
- Enforcement action taken
Licence enforcement action taken by ORR to date
This page contains information about our enforcement action taken against Network Rail and others. It covers enforcement orders, monetary penalties, notices in lieu of enforcement action and breaches where no action was taken.
| Date | Issue | Enforcement action |
|---|---|---|
|
23/07/2012 |
Weaknesses in Network Rail’s plan to deliver performance targets for the long distance sector in 2013-14. This order includes a payment of a reasonable sum should Network Rail fail to meet its commitments, set on a sliding scale of £1.5m for each 0.1 of a percentage point that it falls below the target. (under condition 1 of the network licence in 2012) |
Final order issued under section 55 of the Railways Act 1993 requiring Network Rail to deliver the committed target, including further review and development of its plans. Also included in the final order is a payment if Network Rail fails to meet the target, depending on the level of PPM achieved. |
|
19/01/2012 |
Network Rail’s failure to deliver performance targets for the freight sector; Network Rail to set up and facilitate a recovery board comprising of relevant freight operators to agree steps to be taken to remedy the breach within a specified timescale. (under condition 1 of the network licence in 2012) |
Final order issued under section 55 of the Railways Act 1993, requiring Network Rail to set up and facilitate a recovery board comprising of relevant freight operators to agree the steps to take to remedy the breach, within a specified timescale. |
|
19/01/2012 |
Weaknesses in Network Rail’s plan to deliver performance targets for the long distance sector for 2011-12 and 2012-13; a recovery plan was required. (against Network Rail, under condition 1 of the network licence in 2012) |
Final order issued under section 55 of the Railways Act 1993, requiring Network Rail to produce and implement a plan setting out the steps it will take in the remainder of 2011‐12 and for 2012‐13 to deliver the outputs. |
|
22/11/2010 |
Breach of Network Rail's network licence in relation to the introduction of the Integrated Train Planning System. Continuing breach due to failure to meet required timescales for providing information on changes to the timetable. (Conditions 1 and 2 of the network licence, 2010) |
Penalty of £3m on Network Rail, issued under section 57C of the Railways Act 1993. |
|
13/05/2008 |
Continuing breach of Network Rail's network licence in relation to the planning and execution of engineering work requiring possessions. (Condition 7 of the network licence, 2008) |
Penalty of 14m on Network Rail, issued under section 57C of the Railways Act 1993. |
|
22/04/2008 |
Weaknesses in Network Rail's planning and execution of engineering projects requiring possessions. (Condition 7 of the network licence, 2008) |
Final order issued under section 55 of the Railways Act 1993, requiring Network Rail to produce and implement a plan to address weaknesses. |
|
28/02/2008 |
The likelihood of Network Rail failing to provide infrastructure capability to deliver significant timetable improvements for December 2008. (Condition 7 of the network licence, 2008) |
Provisional order issued under section 55 of the Railways Act 1993, requiring Network Rail to produce and deliver a plan and output in relation to the WCRM project. |
|
28/02/2008 |
Network Rail's decision to take an additional possession at Rugby on 31 December 2007 at late notice, despite the objections of affected operators. (Condition 9 of the network licence, 2008) |
No enforcement action taken. A conclusions document was published on our website. |
|
06/09/2007 |
Weaknesses in Network Rail's planning of the Portsmouth resignalling scheme. Network Rail made decisions risking subsequent failure to meet the reasonable requirements of its customers over a significant period of time. (Condition 7 of the network licence, 2007) |
Penalty of 2.4m on Network Rail, issued under section 57C of the Railways Act 1993. |
|
26/10/2006 |
Network Rail's disposal of land at East Grinstead without ORR consent. (Condition 26 of the network licence, 2006) |
No enforcement action was taken. A warning letter was sent to Network Rail. |
|
12/04/2006 |
Network Rail's failure to publish accurate information about the capability of the network. (Condition 7 of the network licence, 2006) |
Penalty of 250,000 on Network Rail, issued under section 57C of the Railways Act 1993. |
|
02/03/2006 |
Network Rail's failure to ensure accurate information on infrastructure capability was available. (Condition 7 of the network licence, 2006) |
Notice under section 55 of the Railways Act 1993 - decision not to make an Order in relation to contravention of Condition 7. |
|
08/03/2005 |
Network Rail's failure to plan renewal, maintenance and enhancement of the network in a timely and efficient manner (T-12). This related to temporary changes to the national timetable. (Condition 9 of the network licence, 2005) |
Notice under section 55 of the Railways Act 1993 - decision not to make an Order in relation to contravention of Condition 9. |
|
02/09/2004 |
Network Rail's failure to plan renewal, maintenance and enhancement of the network in a timely and efficient manner (T-12). This related to temporary changes to the national timetable. (Condition 9 of the network licence, 2004) |
Notice under section 55 of the Railways Act 1993 - decision not to make an Order in relation to contravention of Condition 9. |
|
14/05/2003 |
The omission of long term expenditure projections from Network Rail's 2003 business plan. (Condition 7 of the network licence, 2003) |
Notice under section 55 of the Railways Act 1993 - decision not to make an Order in relation to contravention of Condition 7. |
|
19/11/2002 |
Railtrack Plc's failure to plan renewal, maintenance and enhancement of the network in a timely and efficient manner at Bletchley engineering works. (Condition 9 of the network licence, 2003) |
Notice under section 55 of the Railways Act 1993 - decision not to make an Order in relation to contravention of Condition 9. |
|
12/04/2002 |
Railtrack Plc's failure to plan the renewal, maintenance and enhancement of the network in a timely and efficient manner for disruptive short notice possessions at Grantham. (Condition 9 of the network licence, 2002) |
Notice under section 55 of the Railways Act 1993 - decision not to make an Order in relation to contravention of Condition 9. |
|
25/03/2002 |
South West Trains Limited's failure to provide information on its performance to enable Railtrack Plc to comply with condition 9 of the network licence (T-12). (Condition 14 of its passenger train operator licence, 2002) |
Notice under section 55 of the Railways Act 1993 - decision not to make an Order in relation to contravention of Condition 14. |
|
12/12/2001 |
Railtrack Plc's failure to deliver performance targets in relation to delay minutes. (Condition 7 of the network licence, 2001) |
Penalty of 7.9 million on Railtrack Plc, issued under section 55 of the Railways Act 1993. |
|
28/11/2001 |
Railtrack Plc's failure to plan renewal, maintenance and enhancement of the network in a timely and efficient manner for short notice possessions and driver training at Pelaw junction. (Condition 9 of the network licence, 2001) |
Notice under section 55 of the Railways Act 1993 - decision not to make an Order in relation to contravention of Condition 9. |
|
09/11/2001 |
Railtrack Plc's failure to plan renewal, maintenance and enhancement of the network in a timely and efficient manner for possessions at: Bloxwich - Hednesford & Church Fenton - Milford junction. (Condition 9 of the network licence, 2001) |
Notice under section 55 of the Railways Act 1993 - decision not to make an Order in relation to contravention of Condition 9. |
|
19/03/2001 |
Railtrack Plc's failure to secure the maintenance, renewal and replacement of the network in accordance with best practice and in a timely, economic and efficient manner after the Hatfield rail incident. (Condition 7 of the network licence, 2001) |
Provisional order under section 55 of the Railways Act 1993, requiring Railtrack Plc to restore the normal operation of the network within defined timescales. |
|
02/11/2000 |
Railtrack Plc's failure to plan renewal, maintenance and enhancement of the network in a timely and efficient manner for short notice possessions at Wortley Junction. (Condition 8 of the network licence, 2000) |
Notice under section 55 of the Railways Act 1993 - decision not to make an Order in relation to contravention of Condition 8. |
|
21/09/2000 |
Railtrack Plc's failure to plan renewal, maintenance and enhancement of the network in a timely and efficient manner for possessions at Camden Junction. (Condition 8 of the Network licence, 2000) |
Notice under section 55 of the Railways Act 1993 - decision not to make an Order in relation to contravention of Condition 8. |
|
23/06/2000 |
Railtrack Plc's failure to plan renewal, maintenance and enhancement of the network in a timely and efficient manner for a short notice timetable change at Princes Risborough - Aynho trackworks. (Condition 8 of the network licence, 2000) |
Notice under section 55 of the Railways Act 1993 - decision not to make an Order in relation to contravention of Condition 8. |
|
20/06/2000 |
Railtrack Plc's failure to plan renewal, maintenance and enhancement of the network in a timely and efficient manner for a short notice timetable change at Hereford to Abergavenny engineering works. (Condition 8 of the network licence, 2000) |
Notice under section 55 of the Railways Act 1993 - decision not to make an Order in relation to contravention of Condition 8. |
|
04/05/2000 |
Railtrack Plc's failure to deliver West Coast modernisation with the efficiency of an experienced infrastructure operator and controller.(Condition 7 of the network licence, 2000) |
Final order under section 55 of the Railways Act 1993. Detailing Railtracks required compliance to condition 7. |
|
24/11/1999 |
Railtrack Plc's failure to deliver performance targets in relation to delay minutes. (Condition 7 of the network licence,1999) |
Final order under section 55 of the Railways Act 1993, to ensure that the minutes delay in the total period is at least 12.7 per cent less than the minutes delay in the base year. |
|
29/10/1999 |
Railtrack Plc's failure to plan renewal, maintenance and enhancement of the network in a timely and efficient manner for the resignalling project in the Dartford Area. (Condition 8 of the network licence) |
Notice under section 55 of the Railways Act 1993 - decision not to make an Order in relation to contravention of Condition 8. |
|
08/09/1999 |
National Rail Enquiry Service's (NRES) non-compliance with answering targets pending investigation of the achievability of the targets. (Condition 7 of passenger train operator licences, 1999) |
No enforcement action taken. We reminded NRES it must plan for capacity as it was already subject to an enforcement order, imposed on 4 December 1998. |
|
04/12/1998 |
NRES' failure to meet telephone call answering targets. (Condition 7 of all franchised passenger train operator licences in 1998) |
Final order on NRES under section 55 of the Railways Act 1993, which remained in place until performance was consistently meeting the target. |
|
16/07/1998 |
Railtrack's 1998 Network Management Statement published the commitments it had given detailing where it needed to take action to secure compliance with its obligations under Condition 7. (Condition 7 of network licence, 1998) |
No enforcement action taken but an ORR statement was published requiring Railtrack to set targets for activities. |
|
23/10/1997 |
Failure of all franchised passenger train operators to ensure that calls are answered with expected answering targets for NRES. (Condition 7 of passenger train operator licences, 1997) |
Penalties totalling 350,000 (250,000 in September and 100,000 in October) on all franchised passenger train operators, issued under section 55 of the Railways Act 1993. |
|
15/08/1997 |
NRES' failure to meet telephone call answering targets. (Condition 7 of all franchised passenger train operator licences in 1997) |
Final order on NRES, under section 55 of the Railways Act 1993 as too many calls were still going unanswered. |
|
12/03/1997 |
LTS Rail Limited's failure to comply with the Ticketing and Settlement Agreement and Travelcard agreement. (Condition 7 of its passenger train operator licence, 1997) |
Notice under section 55 of the Railways Act 1993 - decision not to make a further Order in relation to contravention of Condition 7. |
|
Northern Spirit Limited's (Regional North East Railways) failure to maintain station ticket office opening hours (Condition 7 of its passenger train operator licence, 1997). |
||
|
26/06/1996 |
West Anglia Great Northern Railway Limited's failure to comply with the Telephone Enquiry Bureau scheme. (Condition 7 of its passenger train operator licence, 1996) |
Notice under section 55 of the Railways Act 1993 - decision not to make a further Order in relation to contravention of Condition 7. |
Last updated: February 2013
