Sections 22 and 22a - amendments to track access contracts

In line with the Industry code of practice and the review of our criteria and procedures, Network Rail has now assumed responsibility for consulting on the majority of proposed new contracts and amendments. Accordingly, please check Network Rail's consultation webpages (select Track Access) as well as our own when looking for details of current consultations.

Applications under sections 22/22A , relating to the proposed new Track Access Contract for West Coast Trains Limited, can be found at West Coast Trains TAC.

TOC / FOC Section Name Date consultation closes Links to documents
Arriva Trains Wales 22 27th SA Closed - undertaken by Network Rail Draft agreement
Application form
Chiltern Railways 22 44th SA Closed - undertaken by Network Rail Draft agreement
Application form
Chiltern Railways 22 53rd SA Closed - undertaken by Network Rail Draft agreement
Application form
First Capital Connect 22 24th SA  

Draft agreement
Application form

First ScotRail 22 34th SA Closed - undertaken by Network Rail Draft agreement
Application form
Correspondence
EWS and Network Rail response - 4 Nov 2008
New Southern Railway 22 23rd SG SA Closed - undertaken by Network Rail Draft agreement
Application form
First Capital Connect 22 22nd SG SA Closed - undertaken by Network Rail Draft agreement
Application form
Stagecoach South Western Trains 22 25th SA Closed - undertaken by Network Rail Draft agreement
Application form
London Midland 22 7th SA Closed - undertaken by Network Rail Draft agreement
Application form
London Eastern Railway 22 22nd SA Closed - undertaken by Network Rail Draft agreement
Application form
Timetable Change summary
Freightliner Heavy Haul 22 6th SA   Draft agreement
Application form
Cordon Cap table
Commentary
Table of Rights
East Midlands Trains 22 8th SA Closed - undertaken by Network Rail

Draft agreement
Application form
Draft schedules
Midland Main Line Freight Capacity Report October 2008 
Responses
Freightliner (redacted) - 1 Oct 2008
EWS - 26 Sep 2008
Northern Rail - 1 Oct 2008
Passenger Focus - 26 Sep 2008
London TravelWatch - 11 Sep 2008
First GB Railfreight (redacted) - 22 Sep 2008
London TravelWatch - 30 Oct 2008
Further correspondence
Freightliner further comments - 6 Nov 2008
EWS further comments - 4 Nov 2008
EMT letter to London TravelWatch - 4 Nov 2008
EMT letter to Passenger Focus - 19 Nov 2008
ORR letter to the parties - 4 Nov 2008
NR/EMT letter to ORR - 7 Nov 2008
NR/EMT letter to ORR - 12 Nov 2008
ORR's letter to the parties - 9 Oct 2008
Network Rail/East Midlands Trains joint response - 22 Oct 2008

New Southern Railway Ltd 22a 27th SA 4 Nov 2008 Application form
Draft agreement
Responses
Southern response to WCT - 17 Nov
Network Rail response to WCT - 17 Nov
Network Rail response to LOROL - 24 Nov
Network Rail response to TfL - 24 Nov
Network Rail response to EWS - 24 Nov
Network Rail – 24 Oct
Southern – 3 Nov
West Coast Trains – 5 Nov
LOROL
TfL – 4 Nov
DfT – 4 Nov
London TravelWatch – 4 Nov
EWS – 5 Nov
Passenger Focus – 6 Nov
NXEC Trains Ltd 22a 23rd SA Closed Application form
Draft contract
Responses
Network Rail - 18 July 2008
CrossCountry Trains - 18 July 2008
Department for Transport - 21 July 2008
East Midlands Trains - 18 July 2008
EWS - 21 July 2008
Freightliner - 15 July 2008
Grand Union - 15 July 2008
Hull Trains - 26 June 2008
Hull Trains - 18 July 2008
London TravelWatch - 11 July 2008
Nexus - 25 June 2008
Northern - 24 July 2008
TransPennine Express - 17 July 2008
NXEC comments - 24 July 2008
Hull Trains Company Limited 22a 25th SA Closed Application form
Draft agreement
Network Rail response
Hull Trains comments
Responses:
EWS - 18 July 2008
DfT - 17 July 2008
Freightliner - 15 July 2008
NXEC - 15 July 2008
NXEC Trains Ltd 22a 22nd SA Closed Application form
Draft agreement
NXEC comments
Responses
Network Rail
DfT
EWS
Passenger Focus
Grand Central Railway Company Limited 22a 7th SA Closed Application form
Draft agreement
Grand Central response
Network Rail response
Department for Transport response
EWS response
First Capital Connect response
Hull Trains response
Nexus response
NXEC response
Passenger Focus response
TransPennine Express response
Grand Central comments
Northern Rail 22A 14th SA Closed - undertaken by Network Rail Application form
Draft agreement

Last updated 21 November 2008