ORR - THE OFFICE OF RAIL REGULATION - WWW.RAIL-REG.GOV.UK

Applications and decisions - Stations

When considering applications for approval, the Office of Rail Regulation (ORR) generally consults certain statutory bodies and other potentially affected parties as appropriate to ensure that their views on the implications of the proposed contract or contract amendment are sought and taken into account.

All approved agreements and subsequently approved amendments are held on the ORR's public register. Where, in significant cases, the ORR has published decisions for approvals given, these decisions and the background papers from the relevant consultation exercise will also be available here.

Current applications & decisions

Applicant Document
East Midlands Trains Ltd Application form
  Agreement proposed by EMT
  Representations by First Capital Connect
  Agreement proposed by FCC
  Representations by Department for Transport
  Directions
Reasons document
Directed contract
Grand Central Railway Company Limited Application form
Proposed Station Access Agreement
Representation by Great North Eastern Railway Ltd
Further letter from GNER
Grand Central response to GNER letter
Directions
Reasons document
Directed contract
First ScotRail Limited Application form
Proposed Station Access Agreement (Schedule A)
CoPmparison of proposed Agreement against template Agreement (Schedule B)
Letter - Professional Project Management Ltd to Infratil Airport Holdings Ltd (Schedule C)

Letter - First ScotRail Ltd to Glasgow Prestwick Airport Ltd

Representation by Glasgow Prestwick Airport Ltd
Appendices (A to E) to Glasgow Prestwick Airport Ltd's representations
Appendix A to D
Appendix E
Further representations from Glasgow Prestwick Airport Limited together with Annexures A, B, C and E and answers to questions from ORR
Addendum to the Representations made by Glasgow Prestwick Airport dated 29 March 2006
GPA Airtrain Contribution Comparison Final Requisition Answers
PPM Letter
Further representations from First ScotRail Limited
First ScotRail Letter 1
Identify the methodology and calculate the appropriate access charge for Glasgow Prestwick Airport Rail Facility
Consultation responses
Transport Scotland Response
SPT Response
Annexure D from Glasgow Prestwick Airport Limited
Annexure D part 1 requisitions
Glasgow Prestwick Airport Limited's answers to further questions from ORR and further representations
Part 1
Part 2
Glasgow Prestwick Airport Limited's answers to further questions from ORR
Part 3
Part 3 Annex 1A
Part 3 Supporting documents
Part 3 Supporting Documents part 2
ScotRail response to Glasgow Prestwick Airport representations
Plan submitted by First Scotrail to be appended to the proposed Station Access Agreement
Further plan submitted by First Scotrail to be appended to the proposed Station Access Agreement

Directions Part 1 - 21 May 2007
Directions Part 2
Variations - 24 May 2007
Reasons document Part 1 - 27 May 2007
Reasons document Part 2 - 27 May 2007
Variations - 12 June 2007
Signed contract - 18 June 2007