Home > About

Key dates

The information below summarises the main milestones of the PR13 process and should help you decide when and where you need to get involved.

Please use the mouse scroll-wheel, select the dates or the arrows to move the interactive timeline in the desired direction. You can also view an accessible version of the milestones.

  • PR13 first consultation document

    Consultation
    On 25 May we published our first PR13 consultation document.

  • PR13 July consultation events

    Consultation event ORR hosted consultation events on PR13 held in Edinburgh, Cardiff, London and Manchester. Additional dates were 11, 12 and 21 July.

  • Performance regime workshop

    Workshop
    ORR hosted workshop on the Schedule 8 performance regime.

  • NR efficient expendibure consultation

    Consultation
    Online publication of our document on how we will assess Network Rail's efficient expenditure.

  • First consultation closes

    Consultation closed
    Our first consultation document published on 25 May closes.

  • NR efficient expenditure workshop

    Workshop ORR hosted workshop on our document discussing how we should assess Network Rail's efficient expenditure.

  • Incentives workshop

    Workshop
    ORR hosted workshop on incentives.

  • Initial industry plans published

    Publication The initial industry plans (IIPs) for England & Wales and Scotland are published, setting out the industry’s view on what should be delivered in the next control period and at what cost.

  • On-rail competition consultation

    Consultation
    We publish a review of the role of open access operators on-rail competition.

  • Initial industry plan views sought

    Consultation We seek views on the IIPs (PDF 53 Kb). This will not be a formal consultation, but an opportunity to get any further views before we produce our advice to ministers.

  • Feedback on NR efficient expenditure

    Feedback
    We receive stakeholder feedback on our 26 July 2011 efficient expenditure consultation document.

  • Possessions workshop

    Workshop
    ORR hosted workshop on Schedule 4 possessions regime

  • Transport Scotland consultation

    Consultation Transport Scotland consults on the contract for passenger services and priorities for rail beyond 2014, which will feed into the development of the High-Level Output Specification in Scotland.

  • Initial industry plan feedback

    Feedback
    We receive views on the IIP by this date.

  • On-rail competition consultation closes

    Consultation closed
    The deadline for comments on our review of the role of open access operators in on-rail competition.

  • Incentives consultation launched

    Consultation Consultation on detailed incentives issues and proposals.

  • PR13 incentives workshop

    Workshop
    ORR hosted workshop on the incentives consultation.

  • Incentives consultation closes

    Consultation closed
    Consultation closes on our consultation on incentives.

  • Advice to ministers published

    Publication We published our ‘advice to ministers’ (for both England & Wales and Scotland) and issued our review initiation notice formally starting PR13.

  • NR funding framework published

    Publication We publish our Financial and incentive framework for CP5, setting out the approach we will be taking on the financial and incentive framework following consultations on these areas in December 2011 and May 2011, along with our conclusions on our consultation on on-rail competition last October.


  • Consultation

    Consultation We consult on exposing train operators to changes in Network Rail's costs at periodic reviews and how our route-based efficiency benefit sharing mechanism should interact with alliancing arrangements.

  • Consultation

    Consultation
    We consult on the variable usage charge and on a freight-specific charge.

  • Workshop on track access charges

    Workshop Workshop on track access charges: cap on variable usage charge and freight-specific charge.

  • Consultation closes

    Consultation closed Consultation closes on exposing train operators to changes in Network Rail's costs at periodic reviews and on how our route-based efficiency benefit sharing mechanism should interact with alliancing arrangements.

  • Consultation closes

    Consultation closed
    Our consultation on caps and mark-ups on certain freight track access charges closes.

  • HLOSs/SoFAs published

    Publication Secretary of State for Transport and Scottish Ministers publish their high level output specifications (HLOSs) and statement of funds available (SoFAs).

  • Consultation on detailed financial framework issues

    Consultation We consult on detailed financial issues concerning Network Rail's financial framework for CP5.

  • Consultation on outputs and framework of enablers and KPIs

    Consultation We consult on the outputs Network Rail should be required to deliver, and the wider framework of enablers and monitoring KPIs.

  • Consultation closes

    Consultation closed
    Consultation ends on the variable usage charge and on a freight-specific charge.

  • Consultation closes

    Consultation closed
    Our Consultation on financial issues for Network Rail in CP5 closes.

  • Consultation closes

    Consultation closed
    Our consultation on Network Rail's output framework for 2014-19 closes.

  • Consultation

    Consultation
    We consult on more detailed issues relating to Schedules 4 and 8 restrictions of use and performance regimes.

  • Publication

    Publication
    We publish our decisions following our consultation on detailed financial issues concerning Network Rail's financial framework.

  • Consultation

    Consultation
    We consult on the proposals for reforming the volume incentive.

  • Publication

    Publication
    We published our conclusions on aligning incentives to improve efficiency, following our consultation on 3 May 2012.

  • ORR invites comments on strategic business plan

    Feedback
    Network Rail publishes its strategic business plan (SBP). ORR invites stakeholder comments on SBP.

  • Publication

    Publication
    We publish our decisions on caps for freight charges for CP5.

  • Workshop on strategic business plan

    Workshop
    Workshop on Network Rail's strategic business plan.

  • Biomass consultation launches

    Consultation
    ORR consults on a freight specific charge for biomass.

  • Deadline for comments on Network Rail’s SBP

    Feedback
    Stakeholder comments on Network Rail's strategic business plan received by this date.

  • Biomass consultation closes

    Consultation closed
    Deadline for response to consultation on a freight specific charge for biomass.

  • Consultation

    Consultation
    We consult on technical issues relating to traction electricity charges.

  • Draft determination consultation launches

    Consultation
    We publish our draft determination.

  • Strategic regulatory statement

    Publication
    We publish our draft strategic regulatory statement.

  • Consultation launches

    Consultation
    Consultation on proposed contractual and licence changes to implement the proposals in our draft determination.

  • Consultations close

    Consultation closed
    The consultations on our draft determination and proposed contractual and licence change to implement the determination both close.

  • Final determination

    Publication
    We publish our final determination and strategic regulatory statement.

  • Final access charges approved

    Approved Final access charges (price lists/charge schedules) are audited and approved by us. Review notices are served which start the formal implementation of PR13. (subsequent dates depend on exactly when the review notices are issued).

  • Review notices objections deadline

    Deadline Final point (specific date to be defined) at which objections could be made to our review notices (not less than six weeks from the date of publication of the review notice).

  • Notice of agreement published

    Publication
    We issue notice of agreement (specific date to be defined).

  • Implementation notice published

    Publication
    We issue our review implementation notice (specific date to be defined).

  • NR delivery plan published

    Publication
    Network Rail publishes its delivery plan.

  • PR13 determination implementation

    Implementation Implementation of PR13 determination and start of CP5.

Key dates accessible version

25/05/11
05,11,12
& 21/07/11
ORR hosted consultation events on PR13 held in Edinburgh, Cardiff, London and Manchester
25/07/11
ORR hosted workshop on the Schedule 8 performance regime
26/07/11
Online publication of our document on how we will assess Network Rail's efficient expenditure
02/09/11
Our first consultation document published 25 May closes
21/09/11
ORR hosted workshop on our document discussing how we should assess Network Rail's efficient expenditure
23/09/11
ORR hosted workshop on incentives
By 30/09/11
The initial industry plans (IIPs) for England & Wales and Scotland are published, setting out the industry’s view on what should be delivered in the next control period and at what cost
By 30/09/11
01/10/11
We seek views on the IIPs (PDF 53 Kb)
This will not be a formal consultation, but an opportunity to get any further views before we produce our advice to ministers
14/10/11
We receive stakeholder feedback on our 26 July 2011 efficient expenditure consultation document
11/11/11
ORR hosted workshop on Schedule 4 possessions regime
16/11/11
Transport Scotland consults on the contract for passenger services and priorities for rail beyond 2014, which will feed into the development of the High-Level Output Specification in Scotland
18/11/11
We receive views on the IIP by this date
04/12/11
The deadline for comments on our review of the role of open access operators in on-rail competition
14/12/11
Consultation on detailed incentives issues and proposals
09/01/12
08/02/12
Consultation closes on our consultation on incentives

Formal review phase

15/03/12
We published our 'advice to ministers' (for both England & Wales and Scotland) and issued our review initiation notice formally starting PR13
01/05/12
We publish our Financial and incentive framework for CP5 (this document), setting out the approach we will be taking on the financial and incentive framework following consultations on these areas in December 2011 and May 2011, along with our conclusions on our consultation on on-rail competition last October
03/05/12
We consult on exposing train operators to changes in Network Rail's costs at periodic reviews and how our route-based efficiency benefit sharing mechanism should interact with alliancing arrangements
17/05/12
We consult on the variable usage charge and on a freight-specific charge
18/05/12
Workshop on track access charges: cap on variable usage charge and freight-specific charge
12/07/12
Consultation closes on exposing train operators to changes in Network Rail's costs at periodic reviews and on how our route-based efficiency benefit sharing mechanism should interact with alliancing arrangements.
31/07/12
Our consultation on caps and mark-ups on certain freight track access charges closes
By 31/07/12
The Secretary of State for Transport and Scottish Ministers publish their HLOSs/SoFAs
By 01/08/12
We consult on detailed financial issues concerning Network Rail's financial framework for CP5
By 01/08/12
We consult on the outputs Network Rail should be required to deliver, and the wider framework of enablers and monitoring KPIs
10/08/12
Consultation ends on the variable usage charge and on a freight-specific charge
26/09/12
Our Consultation on financial issues for Network Rail in CP5 closes
28/09/12
26/11/12
We consult on more detailed issues relating to Schedules 4 and 8 restrictions of use and performance regimes
13/12/12
We publish our decisions following our consultation on detailed financial issues concerning Network Rail's financial framework
18/12/12
18/12/12
We published our conclusions on aligning incentives to improve efficiency, following our consultation on 3 May 2012
08/01/13
Network Rail publishes its strategic business plan (SBP). ORR invites stakeholder comments on SBP
11/01/13
13/02/13
Workshop on Network Rail's strategic business plan
15/02/13
19/02/13
Stakeholder comments on Network Rail's strategic business plan received by this date
28/03/13
Deadline for response to consultation on a freight specific charge for biomass
10/04/13
We consult on technical issues relating to traction electricity charges
12/06/13
We publish our draft determination
Jun 2013
We publish our draft strategic regulatory statement
12/07/13
Consultation on proposed contractual and licence changes to implement the proposals in our draft determination
04/09/13
The consultations on our draft determination and proposed contractual and licence change to implement the determination both close
31/10/13
We publish our final determination and strategic regulatory statement

Implementation phase (assuming no objections)

Nov/Dec 13
Final access charges (price lists/charge schedules) are audited and approved by us. Review notices are served which start the formal implementation of PR13. (subsequent dates depend on exactly when the review notices are issued)
Jan/Feb 14
Final point (specific date to be defined) at which objections could be made to our review notices (not less than six weeks from the date of publication of the review notice)
Jan/Feb 14
We issue notice of agreement (specific date to be defined)
Feb/Mar 14
We issue our review implementation notice (specific date to be defined)
By 31/03/14
Network Rail publishes its delivery plan
01/04/14
Implementation of PR13 determination and start of CP5.